Scheduled agent running late

I have some scheduled agents running on an OS400 Domino server. My problem is that some of the agents are not running on their scheduled time. They are running 2hours late. I know there is a setting to limit the number of simultaneous agents and it is set to 7, which is more than enough. Also they always seem to run at the same time every day. Some agents run on time however.

Any suggestions please? I need to run the agents at specific times due to data import/export synchronisation.

Subject: Scheduled agent running late

Try this document from Julie Kadashevich’s Agent FAQ:

Regards

Byju Joy

Subject: RE: Scheduled agent running late

Thanks, the article has lots of interesting settings which are new to me. Will try them out.