Hi to all, I have to migrate a 6.5 server to Domino 8.
Do you think i have to perform the same following tasks befor launching the server as we did form 6 to 7?
:
C:[…]dominodata\nfixup names.nsf –f –j – v – lC:\ […]dominodata\ nfixup admin4.nsf –f –j – v – lC:\ […]dominodata\ncompact names.nsf –c –i –k–fC:\ […]dominodata\ncompact admin4.nsf –c –i –k–f
thanks in advance for your answers.
Bern’
Subject: Re: Migration question
While it’s not recommended per the ND8 Deployment guide, running maintenance on your Domino-critical databases during an upgrade is a recommendable practice to ensure the integrity of your data.
Subject: Re: Migration question - Clarification
I should say, while it’s not explicitly recommended by the ND8 Deployment Guide, running the maintenance you referenced is advisable.
Subject: Thanks for your answer…
but we did it this way and it all worked out.