How can I include many dates (5) in the first column of a calendar view so that meetings on those dates are shown on respective days in the calender view?

I have a form with 5 date fields for 5 different meetings. When this form is created I want 5 entries to be shown in calendar view for the respective dates.

Subject: How can I include many dates (5) in the first column of a calendar view so that meetings on those dates are shown on respective days in the calender view?

Create a computed field on you document which builds a list of dates. (Fields1:Field2:Field3:Field4). Use this field in you date column, and set the column property to show multiple values as separate entries

Subject: RE: How can I include many dates (5) in the first column of a calendar view so that meetings on those dates are shown on respective days in the calender view?

Hi Michelle,Should I use any function before the list (Explode, Implode, etc)?

Also, after I use the list in the date column (first column of caledar view), if any of the dates is missing, nothing will be shown in the calendar view, even if other dates are actually there

Subject: RE: How can I include many dates (5) in the first column of a calendar view so that meetings on those dates are shown on respective days in the calender view?

If you are using a list field, make sure the field contains the list of dates. If so, no need to use Explode. You can directly use the field name mapped to the view’s first column and is to be sorted. Make sure the view of type Calender. Make sure you follow Michelle’s posting.

Subject: RE: How can I include many dates (5) in the first column of a calendar view so that meetings on those dates are shown on respective days in the calender view?

If missing / blank values are a problem, use @Trim to remove them