Date format of 1999 in R6 is different from 2000 and up

We have an application that displays a Notes date field in a view column. In an R5 client, everything works the way we expected: 1999 shows as 1999 and 2000 as 2000.

However, when we open the same view in an R6 client, all the 1999 dates show only ‘99’ and the rest of the dates remain 2000, etc.

Why does R6 treat these 1999 dates different from the others? And more importantly, how do I set it back to 1999?

Subject: Date format of 1999 in R6 is different from 2000 and up

Go to the display styles tab (table with a little beanie), select the date/time options from the drop-down, and select “Always display 4-digit year”. Date/time formatting options in views in ND6 work the same way as they do on date/time fields – R5 only used the default format. (That is, just because YOU always saw 4-digit years doesn’t mean everybody did; it depended on the user’s OS settings.)