Has anyone used DOAS with Domino 8.5.1?
I have had some issues below and wonder if anyone else has run into this?
I have two mail servers that are Domino Clustered.
And sometimes they show SYNCHRONIZED and some time they show NEEDS RESYNC
01/27/2010 09:19:42 AM DAOSMGR: Status started
01/27/2010 09:19:42 AM threadsShouldQuit = FALSE
01/27/2010 09:19:42 AM refcount = 1
01/27/2010 09:19:42 AM threadsCreated = 3
01/27/2010 09:19:42 AM
01/27/2010 09:19:42 AM basePath = F:\Notes\data\
01/27/2010 09:19:42 AM baseStoragePath = F:\Notes\data\DAOS
01/27/2010 09:19:42 AM storagePath = F:\Notes\data\DAOS\0016\
01/27/2010 09:19:42 AM pruneInterval = 9999
01/27/2010 09:19:42 AM maxFilesPerSubcontainer = 40000
01/27/2010 09:19:42 AM maxSubcontainers = 1000
01/27/2010 09:19:42 AM catalogState = SYNCHRONIZED
01/27/2010 09:19:42 AM catalogVersion = 3
01/27/2010 09:19:42 AM catalogMinVersion = 5
01/27/2010 09:19:42 AM
01/27/2010 09:19:42 AM pruneInProcess = FALSE
01/27/2010 09:19:42 AM pruneStartTime = 01/27/2010 02:00:01 AM
01/27/2010 09:19:42 AM pruneEndTime = 01/27/2010 02:00:05 AM
01/27/2010 09:19:42 AM
01/27/2010 09:19:42 AM resyncInProcess = FALSE
01/27/2010 09:19:42 AM resyncStartTime = 01/26/2010 01:26:12 PM
01/27/2010 09:19:42 AM resyncEndTime = 01/26/2010 04:58:16 PM
01/27/2010 09:19:42 AM
01/27/2010 09:19:42 AM dbdeleteInProcess = FALSE
01/27/2010 09:19:42 AM dbdeleteStartTime = 01/27/2010 08:37:07 AM
01/27/2010 09:19:42 AM dbdeleteEndTime = 01/27/2010 08:37:08 AM
01/27/2010 09:19:42 AM DAOSMGR: Status completed
Also not sure if its realted but see these in the log.nsf
01/26/2010 03:52:28 AM AT Collector: Deleted document found for view, ConnectionObservations in activity.nsf, corrective action should be performed
01/26/2010 02:37:40 PM CPU utilization exceeds configured thresholds.
01/26/2010 01:27:02 PM Error connecting to server Remote system no longer responding
01/26/2010 01:35:56 PM Logical disk activity (F) exceeds configured thresholds.
01/26/2010 01:36:37 PM Server not reachable on Cluster Port
Thanks ,
Mark